IT 312 / SIAE-Commerce Project Guide
Your section

3-week timeline

Day 1 is the day the repo is opened to the class. Every team works on its 4 Must items first; Stretch items only after all 4 Musts are merged.

WhenMilestoneDone means
Days 1–2SetupEvery member cloned the repo, ran migrate:fresh --seed and php artisan test (green), and the team merged its first PR: the team table in its module README
Day 3Contracts frozenNo more changes to app/Contracts or app/Events without instructor approval
End of week 1Must items that need no other teamAt least 2 Musts merged per team
Week 2IntegrationsListeners, events and cross-module features merged
End of week 2 (day 10)Checkpoint demo + release v0.1At least 3 Musts merged per team; Platform team tags v0.1 and demos the whole flow
Week 3FinishLast Must, tests, README updates, then Stretch items
Day 18Feature freezeOnly bug fixes and docs merged after this
Day 21Final demo + release v1.0Platform team demos from a fresh clone; each team presents its module in 5 minutes

Rules that keep it on time

  • Platform team reviews every PR within 24 hours.
  • PRs should be small: one Must item or less. A PR touching 20 files is hard to review in a day.
  • If another team blocks you, code against their interface (the starter returns safe data) and tell their liaison the same day.
  • Last merge time before each demo: 6 PM the day before.